Services · Pre-funding

TEV Advisory & Feasibility Studies

Independent techno-economic viability before disbursement: technical soundness, cost credibility, revenue defensibility and debt serviceability.

Overview

What this covers

A Techno-Economic Viability study is the lender’s independent check, commissioned before sanction, that a proposed project is technically sound, that its capital cost estimates are credible, that its revenue and cost projections are defensible and that the resulting debt can be serviced.

Our TEV reports are written for the credit committee, not the promoter. They have supported mandates above ₹15,000 crore across power, renewables, real estate, infrastructure, hospitality, manufacturing and electric mobility.

High-rise construction with tower cranesPhoto: iMahesh · CC BY-SA 4.0 · Wikimedia Commons

Deliverables

What we deliver

  • Site, technology and approvals review
  • Capital-cost benchmarking line by line
  • Revenue, offtake and demand evidence
  • Financial model with DSCR, IRR and stress cases
  • Construction schedule and EPC capability
  • Risk register with monitoring recommendations

Approach

How we work

  1. 01

    Scoping

    Agree the lender’s questions, data list and site programme.

  2. 02

    Site & technical review

    Our own engineers inspect the site and audit the technical basis.

  3. 03

    Cost & revenue testing

    Independent benchmarks and sensitivity analysis.

  4. 04

    Report & presentation

    A defensible report, presented to the credit committee if required.

Typical triggers

When lenders commission it

01

Fresh sanction

New project or greenfield capacity above the bank’s internal threshold, typically before the credit committee meets.

02

Expansion or diversification

Brownfield capacity, a new product line or a change of technology funded on the existing balance sheet.

03

Restructuring

Re-phasing of debt under RBI frameworks, where the lender needs an independent view of residual viability before agreeing terms.

Track record

Selected mandates

Renewable Energy

Serentica Renewables India (KKR & Vedanta Group)

₹4,600+ Cr

Techno-Economic Viability study across two locations covering 152 MW wind, 500 MW solar and 600 MW of battery energy storage.

TEV Study

Infrastructure

Afcons Infrastructure

₹15,000 Cr

Project Monitoring Agency across ten concurrent national mandates including the Nagpur–Mumbai Expressway, Delhi–Meerut RRTS, the Rohtang Pass tunnel and the Mumbai–Pune Missing Link.

Project Monitoring

Construction

Shapoorji Pallonji

₹13,730 Cr

Project Monitoring Agency across ten construction projects including CIDCO Navi Mumbai, MHADA and the Karwar Naval Base.

Project Monitoring

Insights

Related insights

Questions

Frequently asked

How long does a TEV study take?

Four to six weeks for a single-site project once the data list is received, including a site visit by our engineers. Multi-site or portfolio studies are scoped individually.

Who is the report written for?

The lender’s credit committee. The promoter provides data and access, but the opinion, assumptions and sensitivities are ours and are presented to the bank if required.

What does the financial model include?

Project cost, means of finance, revenue and cost build-up, DSCR, IRR and stress cases on capacity utilisation, price, cost overrun and delay. The model is delivered with the report.

Is a TEV study the same as a DPR?

No. A Detailed Project Report is prepared for the promoter to present a project. A TEV study is the lender’s independent check of that project. We prepare both, but never both for the same project.

Enquire

Discuss your project

Share a few details and a partner will respond within one working day.